The Municipal Corporation of Greater Mumbai & Ors. v. Century Textiles & Ind. Ltd., [2025] 1 S.C.R. 313 : 2025 INSC 36

A) ABSTRACT / HEADNOTE

The Municipal Corporation of Greater Mumbai & Ors. v. Century Textiles and Industries Ltd., Civil Appeal No. 6667 of 2023, decided 7 Jan. 2025 (V. Nath & P. B. Varale, JJ.) addresses whether a lessee under a Poorer Classes Accommodation Scheme (PCAS) acquires an enforceable right to a conveyance on expiry of a fixed 28-year lease under the Bombay Improvement Trust Transfer Act, 1925 (the 1925 Act), and whether a writ filed after decades of inaction is barred by delay and laches. The Court held that neither the Board Resolution nor the lease deed or the statutory scheme imposed an automatic, unconditional duty to convey Block-A to the lessee on lease expiry; s.51(2) of the 1925 Act must be read harmoniously with s.48(a) so that conveyance becomes operative only where statutory prerequisites and contractual terms are satisfied. The Court also emphasised that the respondent’s prolonged inactivity (cause of action 1955; writ 2016) manifested inordinate delay and laches which the High Court failed adequately to consider. The appeal was allowed and the High Court order directing conveyance was set aside.

Keywords: conveyance of lease; Bombay Improvement Trust Transfer Act, 1925; s.48; s.51(2); PCAS; delay and laches; writ under Article 226; Section 527 Mumbai Municipal Corporation Act, 1888.

B) CASE DETAILS 

Item Details
Judgement / Cause Title The Municipal Corporation of Greater Mumbai & Ors. v. Century Textiles & Ind. Ltd..
Case Number Civil Appeal No. 6667 of 2023.
Judgement Date 07 January 2025.
Court Supreme Court of India (Bench: Vikram Nath & Prasanna B. Varale, JJ.).
Quorum Division Bench (2 JJ).
Author Vikram Nath, J. (opinion).
Citation [2025] 1 S.C.R. 313 : 2025 INSC 36.
Legal Provisions Involved Bombay Improvement Trust Transfer Act, 1925ss.48, 49, 50, 51; City of Bombay Improvement Act, 1898 (saved schemes); Mumbai Municipal Corporation Act, 1888s.527.
Judgments overruled None reported — High Court order set aside.
Related Law Subjects Municipal law; Property/transfer; Statutory interpretation; Public-private partnership; Administrative law (writ remedies); Limitation/laches.

C) INTRODUCTION AND BACKGROUND OF JUDGEMENT 

The dispute arises out of a century-old PCAS scheme. Century Textiles (Respondent No.1) applied in 1918 to the Improvement Trust to construct workers’ housing under Scheme No.51, undertaking to build many tenements as a pre-condition to lease/benefits. Subsequent events produced:

(i) partial construction (476 rooms and 10 shops by 1925),

(ii) a Board Resolution No.325 dated 31.05.1927 altering the scheme,

(iii) a conveyance of Block-B (10.01.1928) and (iv) a lease of Block-A dated 03.10.1928 for 28 years (commencing 01.04.1927) at nominal rent. The 1898 Act was repealed and the 1925 Act continued the PCAS machinery, including s.48 (lease conditions) and s.51 (default/determination and conveyance).

Respondent claimed conveyance of Block-A on lease expiry (31.03.1955) under s.51(2); the Corporation resisted, asserting no automatic conveyance, that s.48(a) requires restoration in good condition, and that long inaction (no suit till 2016; legal notice 2006 but no suit within six months required by s.527 of the 1888 Act) amounted to laches and defeated equity. The Bombay High Court granted mandamus for conveyance; the Corporation appealed. The Supreme Court’s focus: statutory construction (harmonising ss.48 & 51), contractual document construction (Board minutes, application letters, lease deed), and the equity limitation doctrine of laches/delay when public interest and statutory schemes are implicated.

D) FACTS OF THE CASE 

Respondent No.1’s 1918 application under s.32B of the 1898 Act proposed 44 blocks (980 rooms + 20 shops) as PCAS; Scheme No.51 was notified on 01.05.1918 and possession handed to the Trust in 1919. The company built 476 dwellings and 10 shops by 1925 less than originally proposed.

After the 1925 Act replaced the 1898 Act, the company applied (10.03.1927; letter 20.05.1927 via solicitors C.N. Wadia) to modify Scheme No.51 to accept the reduced construction and sought (inter alia)

(a) lease of Block-A for 28 years

(b) conveyance of Block-B on terms

(c) express statement at paragraph 6 seeking conveyance of Block-A “at the end of period of lease”.

The Board passed Resolution No.325 on 31.05.1927 approving only paragraphs 2 & 4 (lease of Block-A for 28 years; certain layout conditions including a 5-ft strip) but not paragraph 6 which sought conveyance of Block-A. Block-B was conveyed (10.01.1928) on payment. Lease of Block-A granted 03.10.1928 for 28 years at Rs.1 p.a.; the lease expired 31.03.1955. No steps were taken by either side for five decades: the company remained in possession; Corporation did not eject or demand rent. In 2006 the company served a s.527 notice (M.M.C. Act) asking for conveyance; no suit followed. Further correspondence in 2009–2016 sought conveyance and redevelopment; finally a writ petition was filed December 2016. The High Court ordered conveyance; the Corporation appealed. The Supreme Court analysed documents (letters, Board minutes, lease), statutory text and purpose, and the equitable consequences of 51+ years’ delay.

E) LEGAL ISSUES RAISED

  1. Does s.51(2) of the 1925 Act create an unconditional statutory duty on the Board/Corporation to “shall convey” the premises to the lessee on expiry of the lease?

  2. Can s.51(2) be read independently of s.48(a) (obligation to keep and leave premises in good condition) or must the two be harmonised?

  3. Did Board Resolution No.325 or the lease deed incorporate an express contractual covenant to convey Block-A on expiry?

  4. Was the writ under Article 226 maintainable after a delay of 61 years and issuance of a s.527 notice in 2006 without suit within six months?

F) PETITIONER / APPELLANT’S ARGUMENTS

The Corporation argued:

(i) inordinate delay and laches — cause of action arose 1955, but writ filed 2016; s.527 notice of 2006 required suit within six months which was not instituted;

(ii) s.51(2) must be harmoniously read with s.48(a) and cannot create an automatic, unconditional conveyance otherwise s.48(a) is rendered otiose;

(iii) Board Resolution No.325 and the lease do not approve paragraph 6 (conveyance of Block-A) and the High Court misread records;

(iv) even if conveyance arises, “at his cost” implies lessee must pay conversion/registration/stamp costs and take procedural steps the respondent did not do so.

G) RESPONDENT’S ARGUMENTS

Century Textiles contended that the lease and the Board’s acceptance of their application created a contractual expectation and a right to conveyance on expiry; s.51(2) uses mandatory language “shall convey” and is analogous to vesting under s.32I(2) of the repealed 1898 Act; vesting/conveyance is an essential quid pro quo once the lessee performed obligations; the right, once accrued, was indefeasible and immune to laches; internal notings and long possession evidenced acquiescence by the Corporation.

H) JUDGEMENT 

The Court reversed the High Court. Two principal holdings:

(1) Statutory and Contractual Construction — Harmonious Reading: The Court emphasised that statutes must be read as a coherent whole and no provision should be rendered nugatory. s.48(a) imposes an obligation on the lessee to keep and leave the premises in good and substantial repair and condition. s.51(1) addresses default (re-entry) while s.51(2) provides that “where no default is made … the Board shall convey the premise to the lessee at his cost and free of all restrictions.” The Court rejected a literalist reading that “shall” creates an unconditional, automatic conveyance irrespective of compliance with s.48(a) or absence of other prerequisites. Rather, s.51(2) is contingent — conveyance flows only where the statutory scheme and contractual conditions are satisfied; otherwise the obligation to leave the premises in good condition remains meaningful and enforceable. The Court parsed the Board Resolution No.325 and letter of 20.05.1927; crucially paragraph 6 (express request for conveyance of Block-A at lease end) was not approved by the Board, and paragraph 4’s reference to a 5-ft strip did not operate as approval to convey Block-A. Thus no express contractual covenant bound the Corporation to convey Block-A.

(2) Delay and Laches: The Court held that Respondent’s long inaction (51 years without claim; legal notice 2006 followed by no suit within six months; writ only in 2016) amounted to inordinate delay and laches. The High Court’s treatment was cursory; equity disfavors belated petitions that seek to disturb long-settled public schemes and third-party expectations. The Court observed that respondent did not take required steps (payment of conversion/registration costs, institution of suit for specific performance, or serious steps to get conveyance typed/registered) and thus could not invoke s.51(2) opportunistically after decades. Public welfare considerations underlying the 1925 Act (PCAS aimed at poorer classes) meant that converting leasehold into freehold for commercial exploitation would be an abuse of beneficial legislation. For these reasons the High Court order was set aside and the writ dismissed.

a. RATIO DECIDENDI

The decisive ratio: Sections 48(a) and 51(2) of the 1925 Act must be read together so that conveyance under s.51(2) is conditional on compliance with lease obligations and the wider statutory scheme; absence of an express contractual covenant to convey (or Board approval) defeats any claim of automatic conveyance; prolonged inaction by the lessee and failure to take statutory/contractual steps (including payment of conversion costs) and filing a timely suit/new remedy amounts to laches which disentitles equitable relief by mandamus. The Court thus balanced textual, contextual and purposive interpretation with equitable maxims about delay.

b. OBITER DICTA 

The judgment contains important dicta:

(i) public-private PCAS arrangements are quasi-fiduciary and cannot be suborned to private commercial exploitation;

(ii) “shall” in a statute is not invariably absolute — its effect depends on surrounding provisions and purpose;

(iii) internal notings of an administrative body are irrelevant unless formal action is taken by competent authority;

(iv) the Court reinforced established jurisprudence refusing belated challenges that prejudice public administration. These obiter observations guide future disputes under similar welfare statutes and stress that performance, procedural steps and timeliness matter.

c. GUIDELINES

  1. Harmonise conflicting sections: read s.48(a) and s.51(2) to give both operative effect; avoid interpretations making any clause a dead letter.

  2. Documentary primacy: Board resolutions and lease terms govern; only express approval of conveyance (or statutory mandate) will create enforceable right.

  3. Lessee’s active duty: upon lease expiry, lessee must undertake procedural/financial steps (pay conversion/registration/stamp charges; tender documents; sue in time if necessary). Failure to do so weakens equity.

  4. Delay/laches bar: inordinate delay in public-interest contexts is fatal to equitable relief; writs cannot be used to evade limitation and procedural safeguards (e.g., s.527 notice rules).

  5. Protect PCAS purpose: Courts will guard statutory welfare objects against conversion for commercial gain; abuse of beneficial legislation invites refusal of relief.

I) CONCLUSION & COMMENTS 

The Supreme Court adopted a careful, textual-purposeful approach that preserves the integrity of the 1925 Act and the social bargain inherent in PCAS arrangements. The decision underscores two enduring lessons:

(1) legislative words like “shall” must be read within statutory architecture mandatory language cannot be mechanically separated from contextual conditions that give it meaning;

(2) equity demands diligence long inaction, especially where public schemes and third-party expectations are implicated, will foreclose later claims. Practitioners should note the importance of preserving documentary proof of Board approvals and taking timely procedural steps (payment of conversion costs; prompt suit if statutory limitation or prescribed process demands it).

The Court’s insistence on protecting the public welfare object of PCAS indicates reluctance to allow retrospective commercialisation of land allocated for the poor. Future litigants must therefore combine close contract/statute reading with prompt, formal steps to secure purported statutory rights. The judgment will be a touchstone in interpreting obligations/vestings under historical improvement statutes and in evaluating equitable claims after prolonged dormancy.

J) REFERENCES

a. Important Cases Referred

  1. The Municipal Corporation of Greater Mumbai & Ors. v. Century Textiles & Ind. Ltd., [2025] 1 S.C.R. 313 : 2025 INSC 36.

  2. Shri Vallabh Glass Works Ltd. v. Union of India, [1984] 3 SCR 180 : (1984) 3 SCC 362.

  3. Aflatoon v. Lt. Governor of Delhi, [1975] 1 SCR 802 : (1975) 4 SCC 285.

  4. SS Rathore v. State of MP, [1989] Supp. 1 SCR 43 : (1989) 4 SCC 582.

  5. Municipal Corporation of Greater Bombay v. Industrial Development Investment Co. (P) Ltd., [1996] Supp. 5 SCR 551 : (1996) 11 SCC 501.

  6. New Okhla Industrial Development Authority v. Harkishan, [2017] 1 SCR 572 : (2017) 3 SCC 588.

b. Important Statutes Referred

  1. Bombay Improvement Trust Transfer Act, 1925ss.48, 49, 50, 51.

  2. City of Bombay Improvement Act, 1898ss.32B–32I (saved scheme provisions).

  3. Mumbai Municipal Corporation Act, 1888s.527 (notice & limitation).

Share this :
Facebook
Twitter
LinkedIn
WhatsApp